33-39 Knightsbridge

Consented building at 33-39 Knightsbridge shown on the left, currently under construction. The Berkeley Hotel as existing is on the right.

Welcome to the project website for the works at 33-39 Knightsbridge

You may be aware that in autumn 2007 planning consent from Westminster City Council was secured for the redevelopment of the buildings on the 33-39 Knightsbridge site, to provide a new finely designed building with residential and hotel uses related to The Berkeley Hotel.

A planning application seeking amendments to the existing consent for the site was permitted by Westminster City Council at planning committee in March 2018. This application sought to re-organise the internal layout and provide a more contextual design for the Knightsbridge elevation.

Upcoming activities

The excavation contactors, Keltbray, are currently working on site. The target is for the excavation to be complete by the end of March 2020, following which works to build the superstructure will commence.

Previous newsletters

Programme

Basement construction: Q2 2018 – Q1 2020
Superstructure construction start: Q2 2020
Fit out: Q2 2020 – Q4 2020

Contact

If you would like to be added to our email database so that you receive regular updates, please contact our communications advisors Four Communications on:

Tel: 020 3697 4325
Email: 33-39knightsbridge@fourcommunications.com

Community Liaison Group (CLG) meetings are held regularly, which allow our neighbours to meet with representatives of The Berkeley Hotel and the contractors on site. Attendees can hear the latest updates on the ongoing works and ask questions of the project team. If you would like to attend these meetings, please sign up to our email database using the contacts details above to receive information on the date of the next CLG meeting.

The minutes from all previous CLG meetings are available to view below.